Property development is all about persistence. You will never make it to the finish line (at least on time and on budget) without unwavering persistence in almost everything you do. Persistence is about challenging the status quo and not accepting mediocrity. Persistence is about persevering to find a better, faster, cheaper or more valuable alternative to the solution that is first presented. It’s persistence with people that is most important. Persistence to a point of course! It’s a fine line between being just persistent enough to achieve what you need and being a pain in the butt that paradoxically slows things down.
This series ‘Persistence Pays’ is my who’s who list to be persistent with and when you might need to restrain yourself.
Build Contractors and Subcontractors
There are two times you need to persist with build contractors. One, before you have a signed construction contract and two, after you have signed the contract!
When you are scoping projects be gently persistent to extract build rates and pricing that you can use to revise your feasibility and budgets. It’s important to maintain good relationships with contractors for this purpose — once again it’s a two-way street. If you are asking a contractor to give you some pricing for say, the next stage of the failed project you have just taken over, then he’s only doing that where there is a potential job for him down the line. As a developer it’s easy to forget that it may take the contractor some time and effort even to provide indicative pricing, especially if there is substantial construction cost inflation in your market. Any contractor will give you at least one quote, but after that they will increasingly become weary if no job (for them) results. If they are already doing multiple jobs for you then they should oblige providing estimates or quotes. Otherwise though, don’t overstay your welcome. Sometimes when I get conscious of overusing my contacts, I say it’s for feasibility purposes and offer to pay them like a professional cost consulting service.
Once you are in a legal contract, then the contractor should perform as per the letter of the contract and no need for you to have to encourage or persist, correct? Well, oftentimes, no. Let’s call this ‘persistagality’ (persistence with legalities). This means generally persisting with the contractor to get variation price and information requests back to you as soon as possible (irrespective of what the contract says). Reciprocate by helping the contractor out by getting them information in a timely manner as well and they will probably be more forthcoming. When managing the construction contract you need to persist with laying down your expectations of how you will treat additional cost and time claims. The contract, when negotiated correctly, should stipulate the process and what is valid or not, but often there is still a level of interpretation required.
If your project — already resurrected — starts to have its own construction delays and budget overruns (argh, not again!), then persistagalities takes on a whole new meaning. Especially so where additional costs are not clearly covered by liquidated damages or are your responsibility. Now you are compelled to persist, outside the scope of your contract, to limit the damage. Take this example:
As the client you are responsible for supplying an electrical transformer for a new industrial building that you have pre-leased. The transformer delivery is late by a month. That impacts on the contractor’s ability to finish their works as they can’t do their final hook up and test the electrical circuits. The contractor could be entitled to make an extension of time claim for $1,500 per working day or $30,000. Worse, on the other side of the equation you have promised a commencement date to the incoming tenant that will now be delayed — a double whammy! That penalty is another $20,000 hit to your bottom line, not to mention an angry tenant. Persistence to minimize your loss is required. You need to find a creative solution and you may not be able to legally rely on the contractor to help. I found myself in such a situation. We rigged a temporary power supply up to another source. We agreed with the tenant that we would pay their power until the transformer was in place, including a day’s loss of trade to switch the power from temporary to permanent. After convincing the contractor, we modified the existing construction contract to enable works to be completed later when the transformer arrived. That allowed us to get the tenant in on time and removed the potential of costly extensions of time with the contractor. There was the tenant loss of trade cost, some double up of works and a reasonable variation from the contractor to come back on site once the transformer was in place. In the end, because of polite but persistent hustling to obtain agreement from both the tenant and contractor, the damage was much less than it could have been.
Many construction contracts include a defects liability or warranty period. This is when the builder is legally obliged to return to fix any issues or latent defects. This period can be a testing time for your persistagalatic attitude, especially if the builder has left the jobsite and is now immersed in other projects. As time goes on they can get progressively more difficult to contact and coordinate to fix issues. It might be next to impossible if there are no retentions or final payments withheld. Add to that, you can have buyers or tenants who will be on your back to get issues fixed. But now there may be others in the middle, like agents and property managers, making it all the harder to complete tasks. This final effort to complete everything requires developer persistence — don’t underestimate it.
The moral of this section: Persistence has a pay-off. Without persistence, development projects can flounder and every day equals extra dollars.
Andrew Crosby
+64 21 982 444
andrew@xpectproperty.com

Buy the book from Amazon: https://www.amazon.com/dp/1790590884?